TADANO Hydraulic
Truck Cranes TG1500E (150ton) in service
Closely coordinate
the decoration of exhibition in China (Zhuhai).
IHI Crawler Cranes 80ton, 100ton, 150ton, 200ton in service
on this important project
As provide the major
lifting and foundations equipment for a total of approximately 1,000
Nos. of bore piles foundations work at the Mass Transit Railway
Corporation, Hong Kong - The Kowloon Station Project.
Tone
Japan Mach Drill System,Unique Reverse Circulation Down the Hole Method
for 2.0m Dia pile Recorded Drilling Speed over 1.0m Per Hr in Fresh
Granite for Motion
20 Nos. rock
socketed large diameter bore piles were required to be constructed to
35 meters depth in Grade III / II granite rock having a socket length
of between 6 meters and 13 meters with an average length of 10 meters.
The drill work commenced in November 99 and by mid- December the 200
meters of rock socketing work was completed at drilling procress of
between 0.9 and 1.5 meters per hour.